1、将提升门的门扇竖起于洞口中各部位调整至要求尺寸,门扇保持垂直。

1,the door leaf from each part of the vertical adjusting to the required size, the door to keep vertical.

2、将提升门上下门轴初步点焊于洞口预埋件及门扇边梃上,装配时应保证上下门轴在同一垂线上,否则门扇开关阻力大易损坏门轴,初步点焊后在保证门扇不会倾覆的情况下,试手动开关门扇,应能灵活转动无阻滞,再将门轴焊牢。

2,the upper and lower shaft preliminary spot on the embedded part and door window stile, the assembly should be guaranteed under the door in the same vertical line, otherwise the door switch resistance is easy to damage the door, the door leaf after preliminary spot will not overturn the case, try to manually switch the door should be flexible rotation, no block, then the door firmly.

3、将电动开门机安装到位,开门机连杆与门扇联结好。将电插销安装于门扇边梃上,调整至开关门扇后能将门扇锁住为好。

3,the electric door machine installed, open the door machine connecting rod and connecting good door. The electrical plug for door stile, adjusted to switch the door after door lock can be good.

4、按提升门的门型尺寸要求,将门扇中缝及四周密封胶条调整好,作到门扇关闭时缝隙能被胶条封严。

4,according to the gate type size requirements, the door leaf raphe and around the sealant to adjust, so when the door leaf is closed the gap to be rubber seal.

5、电气控制箱装于室内便于检修之处。开门机和电插销安装应符合电气安装规程要求,妥善接好保护地线确保设备及人身安全。

5,an electric control box is arranged in the interior and is convenient for the maintenance. Open the door machine and electric bolt installation should meet the electrical installation requirements, to properly connect the ground protection to ensure the safety of personnel and equipment.

6、检验各有关部分符合要求之后,接通电源按动控制按钮,反复调整行程开关,作到门扇到位后能停止运行。

After 6,inspection departments to meet the requirements of power supply is switched on, press the control button, repeatedly adjust the stroke switch, so the door in place to stop running.